One Green Way
Build status
Concrete and Steel Frame
Over the past three months, construction has progressed at a steady pace. With the steel framework now completed, the concrete works have also been finalised, marking the end of the structural phase of the development. This milestone paves the way for the next stages, including masonry and internal installations. Our efforts remain focused on meeting deadlines and maintaining high quality across all workstream.
Architecture
The site has seen consistent progress across multiple areas, reflecting strong adherence to both the project schedule and established quality standards. The travertine cladding on the façades is advancing well, with particular attention to detailing and the final finish. At the same time, the installation of metal panels is proceeding as planned, enhancing the development’s contemporary aesthetic. Joinery works have surpassed the initial targets with notable progress in the assembly of wardrobes, internal wooden doors, and kitchens, along with the commencement of wine cellar installations in selected units. Glass balustrades are also being installed across external areas and interior staircases, offering both safety and visual lightness. Lift installations are currently underway, with several already progressing to final testing and calibration stages. Externally, work continues on the waterproofing of swimming pools and planters, accompanied by technical tests to ensure watertightness. Pool finishing is also in progress, marking another key stage in the construction process. These advances reflect strong alignment between execution and planning, and reinforce our ongoing commitment to excellence at every phase of the project.
Mechanical, Electrical, Plumbing
Technical systems are now at an advanced stage of implementation. The HVAC systems, which had experienced delays in the previous report, have now caught up and are back on schedule. Electrical works have also progressed, recovering part of the delay, although they remain slightly behind the original plan. Plumbing installations, on the other hand, continue to perform well and remain within the projected schedule.
External Infrastructures
The issue caused by the existing drainage system from neighbouring properties has been resolved, allowing the completion of rainwater, wastewater, and inspection chamber works. With this phase finalised, additional work areas have opened up on the external areas. Paving has begun outside the show homes, including the execution of carports, followed by the surfacing of access roads in front of the apartment buildings. To mitigate the delays caused by third-party interference, a new access road front will be opened adjacent to the homes located at the far end of the development.